I-675/Wilmington Pike Interchange

1. To which Review Panel are you submitting this project?
Transportation & Government Services
2. What is the title of this project?
I-675/Wilmington Pike Interchange
3. Please provide a short, non-technical description of the project, no more than 2-4 sentences.
This project provides interchange modifications to increase capacity of the Wilmington Pike and the existing I-675 ramps. Development of a hospital and medical campus is complete with anticipated future expansion. With the initial phase of major retail, commercial and residential development complete; preliminary planning continues for additional phases adjacent to the interchange. The transportation infrastructure will require expansion to protect the health, safety and welfare of all users.
Requester and Recipient
4. Name of organization making this request
City of Centerville
5. Address
100 West Spring Valley Road
6. City
Centerville
7. State
Ohio
8. Zip Code
45458
9. County
Montgomery
13. State
Alabama
15. County
Auglaize
16. Which category best describes the type of organization that is the recipient for project funding?
Government
Contact Information
17. Name
James G. Brinegar
18. Title
City Engineer
19. Organization
City of Centerville
20. Address
7970 South Suburban Road
21. City
Centerville
22. State
Ohio
23. Zip Code
45458
24. County
Montgomery
25. Phone
(937) 428-4725
26. Email
jbrinegar@centervilleohio.gov
27. Are there other individuals who should receive notices or information related to this project during the review process? If so, please provide name(s), title(s), and email(s). If not, leave blank.
Greg Horn, City Manager
ghorn@centervilleohio.gov
Douglas Spitler, Public Works Director
dspitler@centervilleohio.gov
Project Information
28. City
Centerville
29. County
Montgomery
30. Congressional district
Ohio 10th
Funding Request and Budget Information
31. What is the dollar amount of funding you are seeking in the next year?
$6,000,000.00
32. What is the total project cost?
$30,000,000.00
33. Please list sources, amounts, and status of other funds that this project has previously received or is likely to receive in the future.
Private: $500,000 anticipated
Local: $500,000 anticipated
State: $24,000,000 anticipated
Federal: $5,000,000 anticipated
34. How will the requested funds be used? Please check the category that best fits the project. Then, if you have additional information to provide regarding the use of funds, please provide this information with your supporting documentation (see question #52). EX: if this is for construction, please provide information on the proposed building, its purpose, size and location. If this is for operations, please describe if the money will be used for salaries, rent, equipment, services, etc. The more detail provided, the better the committee can understand the value of your project. This is particularly important for projects seeking operations funding.
Administration or Operations
35. Do you have matching funds raised or committed?
no
37. Do you have a budget with funding details for the project? If so, please send the budget as an attachment under question 52.
No
38. By what date will you be ready to spend the funds?
Within the next 6 months
39. Are there particular state or federal programs or private grants under which this project would qualify for funding? Please be as specific as possible.
State: Ohio Public Works Commission (OPWC): Transportation Review Advisory Council (TRAC)
Federal: Surface Transportation Program(STP)
Community Impact and Job Creation
40. What is the community issue or need that your project will address?
Year 1: 200 jobs created
Year 2: 200 jobs created
Year 6-10: 700 jobs created

This project will provide economic development and job creation to the region. This area of the transportation network will see increased traffic with adjacent development and required expansion to protect the health, safety and welfare of the community.
41. What is the measurement that will be used to determine whether the project was a success?
Measurement of success will be determined by the jobs created and subsequent impact to the region. The ability of the transportation system to support the level of development will further enhance the success of the project.
42. If the project receives funding and is completed, how many DIRECT NEW jobs do you anticipate being CREATED within the next two years?
251-500
43. Please explain how you determined the job creation listed in question 42. One way to support estimated job numbers is to provide examples of similar projects that have created jobs. If you are aware of similar projects, please include details and explain how they relate to your project. This field is limited to 1,000 characters. If you need additional space, please include your information in an attachment, not to exceed 10 pages, which can be uploaded by clicking “yes” on question #52.
Based on the traffic impact study for this area of the City, the provision of the requested improvements to the interchange will allow for a projected amount of additional commercial development along the Wilmington Pike corridor based on the TIS modeling. With this known potential amount of build-out and usage, reduction factor was used to provide a conservative estimate.
44. If the project receives funding and is completed, how many DIRECT EXISTING jobs do you anticipate being RETAINED within the next two years?
101-250
45. Please explain how you determined the job creation listed in question 44. One way to support estimated job numbers is to provide examples of similar projects that have created jobs. If you are aware of similar projects, please include details and explain how they relate to your project. This field is limited to 1,000 characters. If you need additional space, please include your information in an attachment, not to exceed 10 pages, which can be uploaded by clicking “yes” on question #52.
The estimate is based on known existing job number ranges of the existing businesses directly served by the interchange. A LOS decline will reduce business operations and so a conservative reduction was estimated.
46. Using your best guess, over the next 10 years, how many sustained, permanent jobs will the project create and retain if funded and completed? This may include “induced” or “spin-off” jobs.
501-1,000
47. Please explain how you determined the job creation listed in question 46. One way to support estimated job numbers is to provide examples of similar projects that have created jobs. If you are aware of similar projects, please include details and explain how they relate to your project. This field is limited to 1,000 characters. If you need additional space, please include your information in an attachment, not to exceed 10 pages, which can be uploaded by clicking “yes” on question #52.
The estimate is based on conservative projection from expected Miami Valley Hospital South campus expansion and other development areas nearby whose operations improve by upgrading the interchange.
Community Impact and Job Creation Cont.
48. Using your best guess, of the jobs created over the next 10 years, what will the average salary be?
$25,001–$50,000
49. Please explain how you determined the salary amount listed in question 48. This field is limited to 1,000 characters. If you need additional space, please include your information in an attachment, not to exceed 10 pages, which can be uploaded by clicking “yes” on question #52.
Utilized a blended average of expected retail, medical, and professional office salary averages and then applied that blended average to the estimated mix of those uses in the nearby vicinity based on approved zoning and development plans.
50. In which of the following counties do you estimate a substantial number of jobs will be created if the project is funded and completed?
  • Greene
  • Montgomery
51. Are you aware of any opposition to the project? If “yes,” please explain.
No
52. Do you have letters of endorsement or other supporting documents for the project? If “yes,” you may attach one PDF file that contains UP TO TEN PAGES of your supporting documents. This document will be posted online along with your completed questionnaire during the public review period. Please DO NOT exceed 10 pages and do not send separate attachments to the Dayton Development Coalition staff. Project sponsors who exceed 10 pages of supporting documents may be asked to re-submit their project.
No